Deliverable 5.9 Final report on evaluation of technologies and processes

The report presents the technical as well as the economic evaluation of the three different demo sites. Therefore, the system boundaries are carefully chosen and performance indicators are defined within the project. To test the long term stability and the load flexibility of the demo sites, different test profiles were defined and applied to the demo sites.  Generally, all three demo sites reached the defined goal of a methane content of higher than 90 vol.-% at different loads. It was shown that an overall PtG efficiency of higher than 75 % can be achieved. Furthermore, energetic optimizations are discussed within this Deliverable.